Behind the meter, ahead of the grid: five questions on powering data centres

9 November, 2026
By Audrey Lee

Executive summary

Data centres are increasingly building their own power ‘behind the meter’ (BTM) rather than waiting years for a grid connection. We answer five questions on what that means:

  • What is BTM? Power that a data centre produces, stores and uses on its own site. Most sites use it while they wait for a grid connection, but it can stay useful long after the connection arrives.
  • How does it vary by region? BTM is largely a US story for now, driven by long grid queues and plentiful gas. Elsewhere, it is smaller and more often powered by renewables.
  • Can it compete with the grid on cost? Not on average, but grid constraints, cheap local energy and good financing terms can close much of the gap.
  • What else can BTM offer data centres? It can absorb the sudden power swings created by artificial intelligence (AI), cover daily peaks and provide backup, roles that do not end when the grid arrives.
  • What does it mean for investors? BTM is more likely to complement the grid than replace it. For grid investors, the bigger risk is speculative demand, although grid operators and regulators are introducing rules to screen it out. We see battery storage as particularly attractive in the value chain, as it remains useful before and after the grid arrives. 

BTM may get ahead of the grid, but its long-term value lies alongside it.

What is ‘behind the meter’?

‘Behind the meter’ refers to power generated and stored on the customer’s side of the meter, the point that separates the customer’s own system from the utility’s grid (Figure 1). A household with rooftop solar panels is a small-scale example. At a far larger scale, data centres are increasingly turning to BTM because they cannot afford to wait for the grid. Grid connection queues for data centres have lengthened considerably, a theme we explored in our recent paper, Grid capex in the age of renewables and AI (July 2026). In the main data centre hubs of both the US and Europe, a large new site can now face years of delay while new lines and substations are built.1

Figure 1. Two sides of the meter: how a data centre can be powered

Source: Macquarie Asset Management analysis.


BTM arrangements take four main forms (Figure 2):2

  1. Bridge. In a bridge arrangement, onsite generation runs only until the grid connection arrives.
  2. Hybrid. In a hybrid arrangement, onsite generation and the grid share the load over the long term.
  3. Co-location. In co-location, a data centre sits next to an existing power plant and draws on it directly, while the plant usually keeps supplying the grid as well.
  4. Off-grid. The least common form is a fully off-grid, or ‘islanded’, site with no connection to the grid at all.

Figure 2. Bridge, hybrid, co-location or off-grid: the main BTM arrangements 

Source: Macquarie Asset Management analysis.

 

Which technologies power BTM at data centres, and how does their use vary by region?

Developers can choose from gas engines, gas turbines, fuel cells, and solar and wind, usually backed by batteries. Small nuclear reactors are a longer-term option (Figure 3). Which they use varies considerably by region. BTM is happening at scale in the US, mostly with gas, because shale gas is plentiful and can supply power around the clock. Outside the US, where gas is more expensive, BTM leans towards renewables, though volumes are still small.

Figure 3. Data centres can draw on a wide range of onsite technologies

Swipe for more
TechnologyHow it worksTypical roleMain trade-offs
Gas enginesLarge versions of a car engine that burn gas to turn a generator. They come in modular units that can be added one at a time.Main onsite supply, especially where a site grows in stages, and the cheapest onsite gas option. Engines make up about 29% of planned US onsite gas capacity.Needs a steady gas supply, so a site relying on a single pipeline has no backup if it fails. Running costs track gas prices, which are more than four times higher in Europe than in the US.
Gas turbinesBurn gas to spin a turbine, much like a jet engine. Some reuse the hot exhaust to make extra power.3Main supply at larger sites. Turbines make up the biggest share of planned US onsite gas capacity, at 55%.Same gas supply risk as engines, and new machines can take five years or more to arrive.
Fuel cellsTurn gas into electricity through a chemical reaction rather than burning it, a bit like a battery that is constantly refuelled.A niche option today, at about 3% of planned US onsite gas capacity, most of it a single project.4 Lower operational costs than other gas options could give them a bigger role over time.Same gas supply risk as engines. The lowest operational costs among all gas options, with less local air pollution. But they are also the most expensive to build, so still the costliest overall, though subsidies such as the US investment tax credit can help.
Solar and windSolar panels or wind turbines generate power when the sun shines or the wind blows.Rarely used alone. Because output varies, they are paired with a steady source such as gas or the grid, and almost always backed by batteries.The lowest-emission option, and often cheaper than gas even with batteries added. However, they need large sites: powering a 100-megawatt (MW) data centre with solar alone takes around 2,600 hectares.
Batteries5Store electricity and release it when needed.Part of almost every design. They smooth the sudden power swings that AI computing creates and cover the moment a generator trips.Respond in milliseconds but store energy for hours rather than days, so they support other sources rather than replace them.
Small nuclear reactorsUse nuclear fission to produce steady power around the clock.A longer-term option, not yet deployed at data centres.Steady output with lower emissions than gas, but an early-stage technology that is years away and remains expensive.

Sources: BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026; IEA, “Energy and AI”, April 2025; Macquarie Asset Management analysis. The US onsite gas capacity shares shown for engines, turbines and fuel cells refer to planned capacity with a disclosed start date. The remaining 13% comprises 11% from projects that have not disclosed their technology and 2% from projects that combine several technologies.


In the US, BTM deployment is becoming increasingly widespread. US developers have access to the most advanced AI chips. What they lack is the power to run them, because grid connections face long lead times and a fast-growing queue.6 With plentiful gas on hand, many are building their own supply instead. About 124 GW of onsite gas capacity has been announced at US data centres,7 and gas is so far the most common choice, although developers are also weighing batteries, renewables, fuel cells and nuclear.8 Most developers describe this as a bridge until a grid connection arrives.9 However, as US policymakers debate whether data centres should bring their own power supply, onsite generation could become a longer-term complement to the grid.10 Onsite power is projected to serve at least 30% of the growth in US data centre power demand through 2030.11

In Europe, by contrast, the opportunity lies mainly in renewables rather than onsite gas. Renewables and nuclear together are projected to supply 85% of the electricity used by Europe’s data centres by 2030,12 and decarbonisation rules are pushing operators further in that direction.13 Onsite gas is far smaller in scale: announced capacity at European data centres totals 3.5 GW, less than 3% of the US figure. Europe’s main hubs face long waits too, but connections can still be secured within two years in parts of the Nordics, so developers willing to locate there can go straight to the grid.14 Where onsite power is used, it is therefore more likely to be a temporary measure until the grid connection arrives.

In Asia-Pacific, data centres mostly stay on the grid for now, though BTM may be needed where grids struggle to support large AI campuses. China is the mirror image of the US: it has the power but not the chips, and its data centres mostly rely on a grid with ample capacity.15 India has enough generation overall but uneven local grid access, and hyperscalers and leading operators are increasingly contracting offsite renewables and storage through long-term power purchase agreements.16 In Australia, most sites today connect to the less congested distribution grid, and large operators increasingly buy renewables under long-term contracts. However, larger sites will need to connect to some of the most stressed parts of the transmission network, such as Western Sydney.17 For sites in more remote areas, onsite generation, owned either by the data centre or by a third party, could also help ease grid connection constraints (Figure 4).

Figure 4. BTM is taking off in the US, but only just starting elsewhere

Source: Macquarie Asset Management analysis.
 

Can BTM compete with the grid on cost?

On average, no. In the US, the full cost of onsite gas, the most common option today, is $US103–140/megawatt-hour (MWh) depending on the technology, from engines at the low end to fuel cells at the high end, against average industrial grid prices of $US82–93/MWh. But the average hides wide local differences (Figure 5). Grid prices vary from market to market, as does the cost of onsite power. Whether BTM can compete depends on local conditions: how tight the grid is, how cheap local energy is, and how onsite power is financed.

Where grids are tightest, grid power is getting more expensive. In PJM Interconnection (PJM), the largest US grid, which spans 13 states including Virginia, Ohio and Pennsylvania, industrial prices already overlap with the cost of onsite gas. PJM pays power stations to be available at times of peak demand through regular capacity auctions. Prices in each of the last three auctions have hit a regulatory cap; supply is struggling to keep pace with demand.18 Those costs flow through to all customers in the region, data centres included, although fixed-price supply contracts can delay the impact.

Figure 5. US grid prices vary widely by market, and in PJM they already overlap the cost of onsite gas

Source: BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026. Note: Ranges of industrial electricity prices from March 2025 to February 2026. Onsite gas cost range covers engines, combined-cycle turbines and fuel cells serving a 500 MW data centre at 99.9% reliability.

 

In some local areas, energy is cheap enough to make onsite power more competitive, for example where gas cannot reach end markets because of limited pipeline capacity. In West Texas, so much gas has been trapped that local prices averaged below zero for much of the first half of 2026. A data centre built next to that gas could in theory run on fuel that producers would otherwise pay to get rid of, although that advantage may narrow as new pipelines open.19 The same applies where sun and wind are strong and land is plentiful. In those places, solar and wind can often cost less than onsite gas, even with batteries added (Figure 6). The same logic works in reverse in Europe, where gas costs more than four times as much as in the US, which is why onsite options there lean towards renewables.

Figure 6. In the US, onsite gas costs more than the average grid price; solar and wind can cost less but need far more land

Source: BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026. Technology figures are levelised costs; gas assumes a plant serving a 500 MW data centre at 99.9% reliability, excluding carbon prices. Solar and wind exclude round-the-clock backup. Nuclear is for large reactors; small modular reactor costs remain uncertain. Grid prices cover March 2025 to February 2026.

 

However, building on site is capital intensive. Fuel cells, for example, cost about $US3,900/kilowatt (kW) to install before US tax credits.20 Equipment is getting more expensive too. Data centres are now the main force behind rising demand for gas turbines, and the price of the turbines alone is expected to reach $US600/kW by the end of 2027, nearly three times its 2019 level.21 Who pays that upfront cost, and on what terms, therefore matters. Data centres do not always own the plant themselves. Third-party investors can fund and own the equipment, then either sell its power to the data centre under a long-term contract or lease the equipment to it. Whoever owns the plant, lenders focus on the risk that it becomes stranded, for example if a grid connection arrives and the data centre no longer needs it.22 Longer contracts and creditworthy customers reduce that risk, and with it the cost of financing.

There is no single answer, then, to whether BTM can compete on cost. It competes best where grids are tight, local energy is cheap, and onsite plants can be built and financed on good terms. Elsewhere, the grid remains the cheaper source of power. On cost, BTM therefore looks less like a replacement for the grid than a complement to it, filling the gaps where the grid is under strain or local resources make onsite power cheaper.

Beyond speed to power, what else can BTM offer data centres?

Speed to power is the main reason data centres turn to BTM, and for now it is usually planned as a bridge to the grid.23 But once onsite power is in place, it can also make data centres more reliable. AI workloads draw power unevenly: training, the process of building a model, can make demand surge and drop within fractions of a second, while inference, the everyday use of models, follows a steadier daily and weekly rhythm but must respond the moment a request arrives (Figure 7). Onsite batteries and generation can help manage both, giving BTM a role that can outlast the bridge. They do so in three ways: absorbing sudden swings, meeting daily peaks without straining the grid, and providing backup, though all three work best alongside the grid.

Figure 7. Training swings, inference repeats: facility power profiles at 80% average utilisation, by hour of the week

Source: Vercellino, R. et al., “Measurement of Generative AI Workload Power Profiles for Whole-Facility Data Center Infrastructure Planning”, National Laboratory of the Rockies, April 2026. Simulated profiles for a 10 MW site running training and fine-tuning workloads and a 1 MW inference site, each shown as a share of its rated capacity. The training profile is net of queueing: jobs are scheduled first-in-first-out, and at this utilisation around three quarters wait 6.5 hours, so what remains reflects when work arrives rather than an absence of scheduling.

 

The first is absorbing sudden swings. When thousands of chips start and stop a training step together, demand at one site can jump from 6 MW to 30 MW in a quarter of a second.24 Generators cannot keep up: an aeroderivative turbine, a lighter and more flexible turbine design derived from aircraft engines, takes about five minutes to reach full output. Batteries, which respond in milliseconds, fill the gap, which is why they appear in most BTM designs.

The second is meeting daily peaks without straining the grid. We expect inference to account for a growing majority of generative AI electricity demand, as discussed in our recent paper, From prompts to power: generative AI and implications for data centre demand (October 2026). While inference follows a predictable daily rhythm, it often needs to respond the moment a request arrives, meaning its peaks still have to be met. Onsite batteries and generation can cover those peaks, letting a data centre draw less from the network at busy times and connect on a flexible basis, which research suggests can bring new sites online years sooner at lower cost to the wider system.25 Once connected, onsite plants could even sell power back to the grid.26

The third is backup. Many data centres aim for ‘five nines’, or 99.999% uptime, about five minutes without power a year. Operators that lease space to tenants typically guarantee uptime in their contracts and owe service credits if they fall short.27 A grid connection alone usually delivers three to four nines, so data centres add backup power. Traditionally that has meant diesel generators that sit idle until the grid fails, but onsite generation and batteries can supply power every day as well as in an emergency, which is why they can be worth keeping after the grid arrives. More recently, some AI-focused operators have begun to settle for less: many of Meta’s self-built AI data centres target just two nines and have no backup generators. This is a compromise forced by the cost of matching grid-level reliability on site,28 and for inference sites serving critical, real-time services, it may not be an option at all.

In short, although BTM’s initial role of providing speed to power ends once the grid connection is in place, it can still serve three roles: absorbing AI’s sudden swings, helping meet daily peaks and backing up the grid (Figure 8). Batteries in particular are likely to stay valuable long after the grid arrives, as they help with all three roles and are the only option fast enough to absorb AI’s sudden swings.

Figure 8. Beyond speed to power, BTM can play three roles alongside the grid

Source: Macquarie Asset Management analysis.

Is BTM just a bridge or here to stay, and what does that mean for investors across the grid value chain?

For most data centres, BTM is a bridge, and even when it stays, it is likely to work alongside the grid rather than replace it. For investors in the grid, that means the current wave of grid investment is unlikely to be made redundant by data centres building their own power. But BTM will shape what gets built, where, and who carries the risk.

There are two reasons for this. First, data centres are only one driver of grid spending, alongside the growth of renewables, the electrification of transport and heating, and the replacement of ageing networks.29 Second, most data centres building onsite power still want a grid connection in the long term, as the grid remains the cheaper source of power in most markets and the backbone of a site’s reliability.30

Once the grid arrives, some onsite gas plants may stay in service alongside it: most of their cost is in building them, and once built, they are relatively cheap to run (Figure 9). They might then serve as backup or run only at times of peak demand. Either way, the site still connects to the grid. Onsite gas plants simply change how much power the site draws from the grid, and when.

Figure 9. In the US, onsite gas plants are costly to build but relatively cheap to run

Source: BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026. CCGT is combined-cycle gas turbine. Costs assume 99.9% reliability and exclude carbon prices. Fuel and variable operating costs assume a gas price of $US3.97 per million British thermal units (MMBtu). Other costs are mostly the upfront cost of building the plant, along with fixed operating costs and energy storage.

 

Even when onsite backup power stays, what it runs on may change. Across the largest US projects, what is built first is mostly gas, often paired with batteries. Where renewables or nuclear are planned, they tend to come later. Project Jupiter in New Mexico, for example, began construction with up to 2.2 GW of gas microgrids, and has committed to adding 500 MW of renewables by 2028 and another 500 MW by 2032.31 For investors, that could make today’s gas plants a bridge in two senses, to the grid and to cleaner supply on site, and raise the question of how long they will run once cleaner options arrive.

Where BTM does matter for grid investors is in the gap between the demand that is requested and the demand that is real. Some load will be served on site for good.32 The larger risk, however, is speculative demand. In Texas, the grid operator, ERCOT, was tracking around 474 GW of large-load connection requests by mid-2026, about 90% of them from data centres, more than five times the grid’s record peak demand. When it began reviewing these requests in batches under a new state law, less than half had completed the grid studies needed to qualify for the first batch, suggesting many are still at an early or speculative stage.33 Onsite gas shows the same pattern: 40% of announced US capacity has no commissioning date.34 Grid capacity built for forecasts that do not materialise is the real stranding risk.

That risk is increasingly being managed. In Texas, the same law requires developers to post financial security of $US50,000 per MW and, if asked, to show evidence such as equipment orders, land agreements and contracts with end users.35 BTM may even help here: a developer that pays for onsite power while waiting for a connection offers a similar signal, since few would take on that cost for a site it did not intend to build. Some utilities also apply large-load tariffs requiring data centres to make minimum payments over long periods, and in Australia, data centres in Sydney are set to fund new transmission capacity built for them.36 Both put the cost of unused capacity on the customer rather than the network. How far this goes elsewhere in the US is still being decided: federal regulators largely rejected the largest grid operator’s proposed rules for large loads in October 2026, leaving more of the question to individual states.37

Batteries can sit between the two sides of the meter. Their role in absorbing AI’s sudden swings does not depend on the bridge at all, since training loads need fast onsite response whether or not the grid has arrived. Once a site is connected, the same battery could also earn revenue from grid services, by supporting the network at peak times or trading power, although this is still an emerging use. That second role depends on rights rather than physics: a battery behind the meter can sell services to the grid only if its connection and metering arrangements allow it. For battery owners, those arrangements matter as much as the technology.

BTM is therefore more likely to reshape grid investment than replace it. The grid remains the backbone of data centre supply, with its risks increasingly shared with the customers who drive it, and batteries sit between the two, able to serve either side.

Author

  1. JLL, “2026 Global Data Center Outlook”, January 2026; BloombergNEF, “EMEA Data Center Outlook 2026”, September 2026.
  2. International Energy Agency (IEA), “Key Questions on Energy and AI”, April 2026; Regulatory Assistance Project, “Going Off Grid: The False Panacea of Islanding High-Impact Loads”, May 2026.
  3. Known as combined-cycle gas turbine (CCGT).
  4. Oracle’s 2.5-gigawatt (GW) Project Jupiter data center campus in Doña Ana County, New Mexico, US.
  5. Related insight: “Battery storage strategies for revenue stacking and investment success”, October 2025.
  6. For details, see Macquarie Asset Management, “Grid capex in the age of renewables and AI”, July 2026.
  7. BloombergNEF, “EMEA Data Center Outlook 2026”, September 2026.
  8. Cleanview, “Bypassing the Grid: How Data Center Developers Are Building Their Own Power Plants”, February 2026.
  9. BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026.
  10. Utility Dive, “FERC rejects most of PJM’s large load interconnection plan”, October 2026.
  11. Moody’s Ratings, “US data centers pivot to on-site power”, September 2026.
  12. IEA, “Energy and AI”, April 2025.
  13. For example, in Germany, data centres must already match half of their electricity use with renewable power, a share set to rise to 100%. Gleiss Lutz, “Data centre update – draft bill to amend the Energy Efficiency Act”, June 2026.
  14. BloombergNEF, “EMEA Data Center Outlook 2026”, September 2026.
  15. Oxford Institute for Energy Studies, “The China data centre advantage: hype versus reality”, February 2026.
  16. Intralink, “Powering India’s data centre boom”, February 2026; BloombergNEF, “India Data Center Market Prospects”, August 2026.
  17. BloombergNEF, “Data Center Market Prospects: Australia, Japan and Korea”, June 2026; Transgrid, “New transmission capacity in Sydney to be funded by data centres”, August 2026.
  18. PJM Interconnection, “PJM Capacity Auction Procures 138,318 MW of Generation Resources”, July 2026.
  19. Reuters, via Pipeline & Gas Journal, “Waha Gas Prices Hit 16-Week High as Permian Pipeline Constraints Ease”, May 2026.
  20. BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026.
  21. Wood Mackenzie, “Gas turbine prices soar 195% as market faces supply-demand crisis”, April 2026.
  22. A&O Shearman, “Powering data centers: the rise and challenges of the ‘behind the meter’ model”, July 2026.
  23. BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026.
  24. IEA, “Energy and AI”, April 2025.
  25. Camus Energy, encoord and Princeton University ZERO Lab, “Flexible Data Centers: A Faster, More Affordable Path to Power”, December 2025.
  26. This differs from co-location, described in question 1, where a data centre draws on an existing power plant that also supplies the grid. Here, the plant is built for the data centre and would sell surplus power to the grid only once the site has a grid connection.
  27. DatacenterDynamics, “Understanding SLA risk: a guide for data center investors and capital providers”, October 2025.
  28. SemiAnalysis, “US Grid Constraints: Towards 40GW+ of Behind-The-Meter Datacenter by 2028?”, June 2026.
  29. For details, see Macquarie Asset Management, “Grid capex in the age of renewables and AI”, July 2026.
  30. BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026.
  31. Cleanview, “Bypassing the Grid: How Data Center Developers Are Building Their Own Power Plants”, February 2026.
  32. SemiAnalysis, “US Grid Constraints: Towards 40GW+ of Behind-The-Meter Datacenter by 2028?”, June 2026.
  33. ERCOT, “ERCOT Update: Senate Committee on Business & Commerce”, July 2026.
  34. BloombergNEF, “Data Center On-Site Gas Power Costs”, June 2026.
  35. ERCOT, “ERCOT Update: Senate Committee on Business & Commerce”, July 2026.
  36. Transgrid, “New transmission capacity in Sydney to be funded by data centres”, August 2026.
  37. Utility Dive, “FERC rejects most of PJM’s large load interconnection plan”, October 2026.

Important Information

The opinions expressed are those of the author(s) are as of the date indicated and may change based on market and other conditions. The accuracy of the content and its relevance to your client’s particular circumstances is not guaranteed.

This market commentary has been prepared for general informational purposes by the team, who are part of Macquarie Asset Management (MAM), the asset management business of Macquarie Group (Macquarie), and is not a product of the Macquarie Research Department. This market commentary reflects the views of the team and statements in it may differ from the views of others in MAM or of other Macquarie divisions or groups, including Macquarie Research. This market commentary has not been prepared to comply with requirements designed to promote the independence of investment research and is accordingly not subject to any prohibition on dealing ahead of the dissemination of investment research.

Nothing in this market commentary shall be construed as a solicitation to buy or sell any security or other product, or to engage in or refrain from engaging in any transaction. Macquarie conducts a global full-service, integrated investment banking, asset management, and brokerage business. Macquarie may do, and seek to do, business with any of the companies covered in this market commentary. Macquarie has investment banking and other business relationships with a significant number of companies, which may include companies that are discussed in this commentary, and may have positions in financial instruments or other financial interests in the subject matter of this market commentary. As a result, investors should be aware that Macquarie may have a conflict of interest that could affect the objectivity of this market commentary. In preparing this market commentary, we did not take into account the investment objectives, financial situation or needs of any particular client. You should not make an investment decision on the basis of this market commentary. Before making an investment decision you need to consider, with or without the assistance of an adviser, whether the investment is appropriate in light of your particular investment needs, objectives and financial circumstances.

Macquarie salespeople, traders and other professionals may provide oral or written market commentary, analysis, trading strategies or research products to Macquarie’s clients that reflect opinions which are different from or contrary to the opinions expressed in this market commentary. Macquarie’s asset management business (including MAM), principal trading desks and investing businesses may make investment decisions that are inconsistent with the views expressed in this commentary. There are risks involved in investing. The price of securities and other financial products can and does fluctuate and an individual security or financial product may even become valueless. International investors are reminded of the additional risks inherent in international investments, such as currency fluctuations and international or local financial, market, economic, tax or regulatory conditions, which may adversely affect the value of the investment. This market commentary is based on information obtained from sources believed to be reliable, but we do not make any representation or warranty that it is accurate, complete or up to date. We accept no obligation to correct or update the information or opinions in this market commentary. Opinions, information, and data in this market commentary are as of the date indicated on the cover and subject to change without notice. No member of the Macquarie Group accepts any liability whatsoever for any direct, indirect, consequential or other loss arising from any use of this market commentary and/or further communication in relation to this market commentary. Some of the data in this market commentary may be sourced from information and materials published by government or industry bodies or agencies, however this market commentary is neither endorsed nor certified by any such bodies or agencies. This market commentary does not constitute legal, tax accounting or investment advice. Recipients should independently evaluate any specific investment in consultation with their legal, tax, accounting, and investment advisors. Past performance is not indicative of future results.

This market commentary may include forward looking statements, forecasts, estimates, projections, opinions and investment theses, which may be identified by the use of terminology such as “anticipate”, “believe”, “estimate”, “expect”, “intend”, “may”, “can”, “plan”, “will”, “would”, “should”, “seek”, “project”, “continue”, “target” and similar expressions.

No representation is made or will be made that any forward-looking statements will be achieved or will prove to be correct or that any assumptions on which such statements may be based are reasonable. A number of factors could cause actual future results and operations to vary materially and adversely from the forward-looking statements. Qualitative statements regarding political, regulatory, market and economic environments and opportunities are based on the team’s opinion, belief and judgment.

Past performance does not guarantee future results.

Diversification may not protect against market risk.

Macquarie Group, its  employees and officers may act in different, potentially conflicting, roles in providing the financial services referred to in this document. The Macquarie Group entities may from time to time act as trustee, administrator, registrar, custodian, investment manager or investment advisor, representative or otherwise for a product or may be otherwise involved in or with, other products and clients which have similar investment objectives to those of the products described herein. Due to the conflicting nature of these roles, the interests of Macquarie Group may from time to time be inconsistent with the Interests of investors. Macquarie Group entities may receive remuneration as a result of acting in these roles. Macquarie Group has conflict of interest policies which aim to manage conflicts of interest.

All third-party marks cited are the property of their respective owners.

Macquarie Asset Management is a leading global asset manager offering a diverse range of investment solutions, including real assets, real estate, and credit.

 

This information is a general description of Macquarie Asset Management only. The views expressed in this website represent those of the relevant investment team and are subject to change. No information set out above constitutes advice, an advertisement, an invitation, a confirmation, an offer or a solicitation, to buy or sell any security or other financial product or to engage in any investment activity, or an offer of any banking or financial service. Some products and/or services mentioned on this website may not be suitable for you and may not be available in all jurisdictions.

 

Investing involves risk including the possible loss of principal. The investment capabilities described in this website involve risks due, among other things, to the nature of the underlying investments. All examples herein are for illustrative purposes only and there can be no assurance that any particular investment objective will be realized or any investment strategy seeking to achieve such objective will be successful. Past performance is not a reliable indication of future performance.

 

Before acting on any information, you should consider the appropriateness of it having regard to your particular objectives, financial situation and needs and seek advice.

 

Other than Macquarie Bank Limited ABN 46 008 583 542 (“Macquarie Bank”), any Macquarie Group entity noted in this website is not an authorized deposit-taking institution for the purposes of the Banking Act 1959 (Commonwealth of Australia).  The obligations of these other Macquarie Group entities do not represent deposits or other liabilities of Macquarie Bank.  Macquarie Bank does not guarantee or otherwise provide assurance in respect of the obligations of these other Macquarie Group entities.  In addition, if this website relates to an investment, (a) the investor is subject to investment risk including possible delays in repayment and loss of income and principal invested and (b) none of Macquarie Bank or any other Macquarie Group entity guarantees any particular rate of return on or the performance of the investment, nor do they guarantee repayment of capital in respect of the investment.

 

Additional important information (including regional disclosures)

 

[3246420]