The Whitecourt facility, which is comprised of one steam turbine and one generator, uses wood waste to generate electricity. Fluidized bubbling bed boiler combustion is the principal technology for the conversion of biomass for electricity production. The combustion process generates hot gases that in turn produce steam, which is then used to generate electricity in the turbine/ generator. The electricity generated by the Whitecourt facility is delivered to the Alberta power grid.
Start of Operations:
1994
Ownership Interest:
100%
Size:
28 MW
Availability*:
88.4%*
Power Purchase Agreement Expiry:
2014
Customer:
TransAlta Utilities Corp.
Other Contracts:
Fuel supply agreement with Millar-Western Pulp Ltd. until 2016.