- Provision of subordinated loan to the SeoulChuncheon Expressway project (investment commitment of KRW 79.4 billion)
- Completion of acquisition of 75% of equity and subordinated debt in the Gwangju 2nd Beltway, Section 3-1 project
|
| November 2004 |
- Refinancing the third party provided senior loan for the Gwangju 2nd Beltway Section 1 project with an MKIF provided loan
|
| October 2004 |
- Completion of acquisition of 24.1% equity and subordinated loan interests in Incheon International Expressway project
|
| September 2004 |
- The first installment payment for the Cheonan-Nonsan Expressway project completed
- The fourth General Shareholders' Meeting held on September 10
- Distribution of KRW 13.8 billion paid
|
| July 2004 |
- The 4th fund raising completed – secured additional Capital Commitments of KRW 630.2 billion (total commitments of KRW 1,260.4 billion)
|
| March 2004 |
- Commitment to provide 49% of equity and subordinated loans to the Machang Bridge project
- Completion of acquisition of 99.2% of the equity and shareholder loans in the Baekyang Tunnel project
- The third General Shareholders' Meeting held on March 12
- Distribution of KRW 3.2 billion paid
|
|
|
|